Set perimeter members . . .
|

in prepared opening.
|

Install spanners for the first row,
|

then spacers.
|

Apply precut silicone cushion strips along the inside edges of floor grid members before setting glass panels.
|

Mask edges of each glass panel to prevent damage and assure a neat installation.
|

Using vacuum cups, carefully set each panel into place.
|

Repeat the process . . .
|

for each row.
|

Apply clear silicone sealant and remove masking tape.
|
|

Total installation time: approximately 2 hours.
|